*Month 1 (9.15-10.15):
 
*Month 1 (9.15-10.15):
 
**Two units of stone and four units of lumber purchased.
 
**Two units of stone and four units of lumber purchased.
 +
**1428 gp of labor completed.
  
  
  
 
*[[Log of Completed Work on Wolf Keep]]
 
*[[Log of Completed Work on Wolf Keep]]
 
  
 
===Current Labor Totals===
 
===Current Labor Totals===

Revision as of 10:12, 11 April 2017

The Wilderlands of Absalom

Commissioned Chain

  • See this post
  • Will cost 100 gp to install
  • Costs 4500 to commission.
    • Chain is commissioned on 9.14 and will be complete on 11.14

Stables and Hippogriff Aerie

  • Work begins on 9.15 on the Aerie first

Stables

  • Overall Cost of 11,250.
    • 5,625 labor
    • 5,625 materials
      • 2,000 gp in lumber. 0/2000
      • 3,625 gp in stone. 0/3625

Aerie

  • Overall Cost of 3,600.
    • 1800 labor.
      • Four trees of carpenters (639 gp/month) plus laborers
      • Five trees of masons (789 gp/month) plus laborers
    • 1800 materials.
      • 800 stone. 250/800. This translates to seven loads of stone, weighing a total of 1400 stone and taking 2.3 trips in the river boat.
      • 1000 lumber. 500/1000. This translates to 8 loads of lumber, weighing a total of 400 stone and taking 2/3 trip in the river boat.
  • Month 1 (9.15-10.15):
    • Two units of stone and four units of lumber purchased.
    • 1428 gp of labor completed.


Current Labor Totals

  • As of 10.1
  • Carpentry: 480/month
  • Masonry: 600/month

Materials

Onsite

6.14
7.14

Commissioned

Junction warehouse