Wolf Keep Construction Schedule: Difference between revisions
Jump to navigation
Jump to search
Thirdkingdom (talk | contribs) No edit summary |
Thirdkingdom (talk | contribs) |
||
Line 9: | Line 9: | ||
==Stables and Hippogriff Aerie== | ==Stables and Hippogriff Aerie== | ||
*Work begins on 9.15 | *Work begins on 9.15 on the Aerie first | ||
===Stables=== | ===Stables=== | ||
*Overall Cost of 11,250. | *Overall Cost of 11,250. | ||
**5,625 labor | **5,625 labor | ||
**5,625 materials | **5,625 materials | ||
***2,000 gp in lumber. 0/2000 | ***2,000 gp in lumber. 0/2000 | ||
Line 23: | Line 21: | ||
*Overall Cost of 3,600. | *Overall Cost of 3,600. | ||
**1800 labor. | **1800 labor. | ||
*** | ***Four trees of carpenters (480 gp/month) | ||
***Two trees of masons ( | ***Two trees of masons (600 gp/month) | ||
**1800 materials. | **1800 materials. | ||
***800 stone. 0/800 | ***800 stone. 0/800. This translates to seven loads of stone, weighing a total of 1400 stone and taking 2.3 trips in the river boat. | ||
***1000 lumber. 0/1000 | ***1000 lumber. 0/1000. This translates to 8 loads of lumber, weighing a total of 400 stone and taking 2/3 trip in the river boat. | ||
*Month 1 (9.15-10.15): | |||
==Work Complete on Wolf Keep== | ==Work Complete on Wolf Keep== |
Revision as of 16:32, 28 October 2016
Commissioned Chain
- See this post
- Will cost 100 gp to install
- Costs 4500 to commission.
- Chain is commissioned on 9.14 and will be complete on 10.14
Stables and Hippogriff Aerie
- Work begins on 9.15 on the Aerie first
Stables
- Overall Cost of 11,250.
- 5,625 labor
- 5,625 materials
- 2,000 gp in lumber. 0/2000
- 3,625 gp in stone. 0/3625
Aerie
- Overall Cost of 3,600.
- 1800 labor.
- Four trees of carpenters (480 gp/month)
- Two trees of masons (600 gp/month)
- 1800 materials.
- 800 stone. 0/800. This translates to seven loads of stone, weighing a total of 1400 stone and taking 2.3 trips in the river boat.
- 1000 lumber. 0/1000. This translates to 8 loads of lumber, weighing a total of 400 stone and taking 2/3 trip in the river boat.
- 1800 labor.
- Month 1 (9.15-10.15):
Work Complete on Wolf Keep
- As of 8.14
- Wolf Keep needs a total of 10,000 gp worth of work done before it becomes fully functional.
- 2500 carpentry labor-2116/2500
- 2500 gp worth of lumber-2500/2500
- 2500 masonry labor-2121/2500
- 2500 gp worth of stone-2500/2500
- 2500 carpentry labor-2116/2500
Workers Rebuilding the Keep
- One engineer (250 gp/month)
- One master carpenter (40 gp/month, minus 25% efficiency for supervising for total of 30 gp)
- Two journeymen carpenters (30 gp/month, total of 60/month)
- Four apprentice carpenters (15 gp/month, total of 60/month)
- Two journeymen carpenters (30 gp/month, total of 60/month)
- One master carpenter (30 gp/month)
- Two journeymen carpenters (60 gp/month)
- Four apprentice carpenters (60 gp/month)
- Two journeymen carpenters (60 gp/month)
- One master carpenter (30 gp/month)
- Two journeymen carpenters (60 gp/month)
- Four apprentice carpenters (60 gp/month)
- 15 skilled laborers (6 gp/month, total of 18/month)
- 15 unskilled laborers (3 gp/month, total of 21/month)
- Four apprentice carpenters (60 gp/month)
- Two journeymen carpenters (60 gp/month)
- One master mason (40 gp/month, minus 25% efficiency for supervising for total of 30 gp)
- Two journeymen masons (30 gp/month, total of 60/month)
- Four apprentice masons (15 gp/month, total of 45/month)
- Two journeymen masons (30 gp/month, total of 60/month)
- One master mason (30 gp/month)
- Two journeymen masons (60 gp/month)
- Four apprentice masons (60 gp/month)
- Two journeymen masons (60 gp/month)
- One master mason (30 gp/month)
- Two journeymen masons (60 gp/month)
- Four apprentice masons (60 gp/month)
- 15 skilled laborers (6 gp/month, total of 18/month)
- 15 unskilled laborers (3 gp/month, total of 21/month)
- Four apprentice masons (60 gp/month)
- Two journeymen masons (60 gp/month)
Workers Fixing the Basement
- One master mason (40 gp/month)
- Two journeymen masons (total of 60/month)
- Four apprentice masons (total of 45/month)
Work on the basement will be complete 10.1
Current Labor Totals
- As of 8.14
- Carpentry: 585/month
- Masonry: 585/month